Boeing 777X Bad News

Daniel-Fowkes-Profile
30 Oct 2025
3 min read
· Aircraft 
On 22nd June,2023. Boeing 777x aircraft displayed at Paris airshow.

Bad but expected news for the 777X: Boeing reports a $4.9 billion charge due to program delays.

Revealed in the planemaker’s Q3 2025 earnings, the major charge, previously cited by CEO Kelly Ortbeg, follows the planemaker’s continued struggles to secure aircraft approval for entry into service.

The delays were only worsened by comments from Ortbeg in recent months, in which he indicated that the business was firmly behind schedule in obtaining approval for the 777X.

Additionally, the CEO stated that there was a mountain of work still left in the process to certify the jet. While nothing abnormal has been found since, this shows the still strenuous process of getting the plane the formal all-clear.

With Boeing long hoping to launch the 777X next year, that window has become increasingly unlikely as pressure continues to mount on the business and on this eagerly awaited flagship product.

The latest Aircraft by Boeing. Newly Made Aircraft Boeing named as Boeing 777X its a new variant with variable wingtips
The latest Aircraft by Boeing. Newly Made Aircraft Boeing named as Boeing 777X, its a new variant with variable wingtips – Photo: Falcons Spotters (shutterstock)

For the business, a $4.9 billion charge adds to the $10 billion in charges the planemaker has reported thus far for the 777X jet, and the latest costs stem directly from struggles with airline customers and related penalties.

Airlines Hurt From 777X Delays

Late deliveries can have a widespread impact and ultimately affect not only Boeing but also airline customers who, in this case, have purchased the long-haul jet to elevate their widebody flying.

For most businesses, the punt taken to commit to the series was that the aircraft would replace older aircraft and/or fuel growth across the network in a much more efficient manner than previous generations of aircraft.

As a result, airlines will plan delivery windows for their new planes to align with fleet replacement efforts, prospective new route launches and more. This all ties in with future forecasting metrics, finances and more.

However, Boeing has missed these timelines time and time again, forcing airlines to scramble, including Emirates, one of the jet’s biggest backers, which has also been frustrated by the unfolding situation.

Boeing 777X at Dubai Airshow 2023 Display flight
Boeing 777X at Dubai Airshow 2023 Display flight – Photo: Georgi Bidenko (shutterstock)

Emirates’ 777X jets are now half a decade delayed, and as a result, existing aircraft have been retained longer than expected, going against the airline’s long-standing and successful business model.

Additionally, the airline has dove headfirst into a multi-billion-dollar retrofit of its existing aircraft, the 777 and A380, to mitigate some of the 777X delays by bringing older aircraft up to the standards of the new inbound plane.

Latest On The Boeing 777X

When Boeing launched the 777X program in 2013, it outlined a seven-year turnaround to bring the jet to production, certification, and scheduled passenger service.

With this in mind, Boeing wanted the aircraft delivered to customers commencing in 2020; however, given how the latter stages of the 2010s played out, and especially the emergence of the COVID-19 pandemic, this quickly became a far-fetched dream.

From this point forward, Boeing has grappled with delay after delay. While it has on several occasions outlined delivery timelines for the first unit, it has consistently missed these deadlines, leaving its airline customers even more frustrated by failed promises after failed promises.

More recently, Boeing had hoped to deliver the first 777X in 2025; however, by late 2024, this was clearly not possible given the program’s struggles, and the delivery was pushed back until 2026 at the earliest.

A Boeing 777X flight test vehicle taxis out to the runway for a flying display at the 2023 Dubai Airshow
A Boeing 777X flight test vehicle taxis out to the runway for a flying display at the 2023 Dubai Airshow – Photo: Coby Wayne

Now, Boeing is once more in the same predicament it found itself in 12 months ago, with another delivery deadline not being met, and 2026 is not possible either.

As a result, the first delivery of the Boeing 777X is now not expected until 2027 at the earliest. Airlines would argue there’s every chance this is pushed back to 2028 or, at the very least, that it’ll be 2028 when they finally start operating scheduled passenger flights, thus representing an eight-year delay.

Daniel-Fowkes-Profile

ABOUT THE AUTHOR

Daniel Fowkes

Daniel Fowkes is a Melbourne-based aviation analyst and journalist with over a decade of industry experience. As founder of Dj’s Aviation, he delivers trusted analysis on aircraft, airline strategy and global aviation trends for djsaviation.net

More About Author

Leave a Reply

Stay Informed

Get the latest aviation news, analysis and route updates delivered to your inbox.

We respect your privacy. Unsubscribe at any time.

Enjoyed this story?

Make us your go-to for aviation news

Add us as a preferred source on Google and see our latest stories first in Top Stories.

Add Us On Your News Feed